The Cedars Hall Project

Latest news

July 2010
We have identified a Principal Contractor for the building work at Cedars and continue to finalise details of the lease. Watch this space for further updates!

April 2010
The refurbishment specification has gone out to local construction and building firms with an invitation to tender. We will be appointing a contractor in mid-April and aim to be on site to begin refurbishment in May 2010.

As previously, we are very grateful to David Kann Associates for all their hard work in enabling us to move forward with this stage of the project.

November 2009
Hurrah! We have just had confirmation that our planning application has been approved! We would like to thank David Kann Associates for their help in putting the application together and for all the support they have offered us so far in this project.

We can now finalise the refurbishment specification and put the contract out to tender. We are also continuing to finalise the details of our 30 year lease with Harrow Council.

A bit of background...

Kids Can Achieve have been looking at moving to new premises for some time now. After 7 years at our centre in Pinner Green, it is now too small and no longer suitable for the work we do supporting children and young people with additional needs.

Cedars Hall is a former rugby club owned by Harrow Council, approximately 2 miles from our current centre. Together with the local tenants and residents association, Weald TRA, we have developed plans for Cedars to include space for our activities and for community use.

Who will use the Hall

The Cedars Hall project will have three main elements:

  • Bigger premises for Kids Can Achieve providing more space for services, workstations and outdoor play and parking
  • Office space and services space for four other community organisations - WTRA, ADHD Support Harrow, NASH and HOPE
  • A community and resource centre providing a range of services and support for the local community

ADHD Support Harrow, NASH and HOPE offer services which complement our own and will be renting office space from us in Cedars Hall. Co-location with these organisations helps us support families more effectively.

Weald Tenants and Residents Association provide support to residents in the Harrow Weald area. They will have a designated office and priority use of a meeting room to provide a clear point of contact for the residents association and a focus for community issues and activities.

WTRA and other community groups will also have the opportunity to use parts of the centre out of hours. Activities might include exercise classes, training courses or children's parties.

Plans for the Hall

KCA needs more space to deliver the services we provide. Our current premises are much smaller than Cedars Hall and we have no outdoor play space for the children and no parking facilities.

Our plans for the interior of the building include space for the children to play in with classrooms and messy play area, better and more child friendly cooking facilities, rooms for counselling and therapies and separate office space for KCA, WTRA and other partner organisations.

Outside there will be a secure children's play ground, with scope for outdoor play, sports and gardening and nature activities. There will also be onsite parking and bicycles to provide a safe pick up and drop off point for parents and to avoid disruption to residents.

The centre will be in use from 9am to 6pm Monday to Friday, with some use for smaller scale weekend activities. During evenings and weekends, the centre will also be available for small scale use by the wider community.

Timescales

 

 

 

 

 

 

 

Get involved!

If you have any queries regarding our plans for Cedars Hall, there are several ways to learn more about the project:

  • Get in touch! We will be happy to discuss our plans in more detail via telephone or email to info@kidscanachieve.co.uk. Please mark emails 'Cedars Project'.
  • Keep an eye on our website. We will be adding regular updates as the project moves forward.

Kids Can Achieve
29 Pinner Green
Pinner
Middlesex HA5 2AF

020 8868 5629

info@kidscanachieve.co.uk

 

 

Date Action
June and July 2009 Work on final designs and statements for planning submission. Completed
July 2009 Consultation carried out with residents and stakeholders. Completed
End July 2009 Planning application submitted. Completed
November 2009 Planning Permission awarded. Completed
March 2010 Tender issue. Completed
April 2010 Tender returns Completed
May 2010 Appoint contractor
August 2010 Refurbishment begins
April 2011 Cedars Hall opens